Work Profile Report [2W259]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 428/।।।(2)/16-14(मु.मं.घो.)/2015 दि0 23.01.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
11.58
Resanction Cost :
11.58
Tentative Cost :
0.10
Saving
11.48
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
11.48
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Alignment Approved
Sanction on : 9 years 6 months ago
23 Jan 2016
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 4 days 16 hours ago
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में क्षतिपूरक वृक्षारोपण हेतु भूमि आवेदित की गयी है। -- as on 17-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand