Work Profile Report [2W285]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1218/।।।(2)/16-53(एम.एल.ए.)/2015 दि0 27.06.2016
TS Amount (lakhs) : 23.91 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
23.91
Resanction Cost :
23.91
Tentative Cost :
4.35
Saving
19.56
Exp. Upto Last Fy :
4.35
For CFY 2025-2026
Remaining :
19.56
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
4.35
Alignment Approved
Sanction on : 9 years 1 month ago
27 Jun 2016
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 1 year 4 days ago
31 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण कार्य पूर्ण। समरेखण 31.12.2021 को स्वीकृत। वन विभाग के साथ संयुक्त निरीक्षण की कार्यवाही प्रगति पर। -- as on 17-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: