Administrative Approval Detail : शा0सं0 2008/।।।(2)/16-53(एम.एल.ए.)/2015 दि0 27.06.2016
TS Amount (lakhs) : 69.07 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
106.00
Resanction Cost :
106.00
Tentative Cost :
106.00
Exp. Upto Last Fy :
44.85
For CFY 2025-2026
Remaining :
61.15
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
44.85
Work completed
Sanction on : 9 years 1 month ago
27 Jun 2016
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 11 months 1 week ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 03-Feb-2025