Work Profile Report [2W39]

मकड़ाऊ-दशौला मोटर मार्ग (किमी. 6-10)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 127/लो0नि0-1 दि0 16-2-04

TS Amount (lakhs) : 12.35 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

69.50

Resanction Cost :

69.50

Tentative Cost :

69.50

Exp. Upto Last Fy :

49.77

For CFY 2025-2026

Remaining :

19.73

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

49.77

Survey work done

Sanction on : 21 years 5 months ago

16 Feb 2004

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 7 months 1 week from now

15 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
5
5
-

Remark

view all

विभाग द्वारा कई बार सर्वेक्षण कार्य किया गया। ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 17-Jul-2025

Rating : 72

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Bridges on The Basis of AI: