Work Profile Report [2W432]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1541/।।।(2)/20-52(एम.एल.ए.)/2017 टी.सी.
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
34.00
Resanction Cost :
34.00
Tentative Cost :
34.00
Exp. Upto Last Fy :
3.40
For CFY 2025-2026
Remaining :
30.60
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.40
Alignment Approved
Sanction on : 4 years 11 months ago
04 Sep 2020
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 4 months 4 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सर्वेक्षण पूर्ण। समरेेखण दि0 30.07.2022 को स्वीकृत। संयुक्त निरीक्षण हेतु प्रभागीय वनाधिकारी अल्मोड़ा को पत्र प्रेषित। -- as on 03-Jan-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand