Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.500 | 0 | 0.000 | 0.000 |
2W464 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1565/।।।(2)/21-52(एम.एल.ए.)/ 2017 दि0 15.06.2021
TS Amount (lakhs) : 107.71 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
107.71
Resanction Cost :
107.71
Tentative Cost :
107.71
Exp. Upto Last Fy : 88.00
For CFY 2024-2025
Remaining : 19.71
Demand : 5.00
Allotment : 0.00
Exp in CFY : 4.40
Total Up to Date Exp : 92.39
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
15 Jun 2021
Tentative Completion date:
9 months 2 weeks ago
30 Sep 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 13-Jul-2024
Physical Peramenters