Work Profile Report [2W499]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1180/।।।(3)/2021-42(सी0आर0आई0एफ0)/2021 दि0 27.10.2021
TS Amount (lakhs) : 1226.76 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1226.79
Resanction Cost :
1226.79
Tentative Cost :
1085.00
Saving
141.79
Exp. Upto Last Fy :
1,074.41
For CFY 2025-2026
Remaining :
152.38
Demand :
5.00
Allotment :
50.46
Exp in CFY :
0.00
Total Up to Date Exp :
1,074.41
Work completed
Sanction on : 3 years 5 months ago
27 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 months ago
24 Jan 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 141.79 has been recorded as expected cost of work reduced from 1226.79 to 1085.00 . -- as on 11-Apr-2025