Work Profile Report [2W5]

शैल-घुरसौं छाना कुडगोली हवालबाग मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 182/लो.नि.-2/04-8(प्रा.आ.)/04 दि0 12.2.04

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

139.00

Resanction Cost :

139.00

Tentative Cost :

139.00

Exp. Upto Last Fy :

0.28

For CFY 2024-2025

Remaining :

138.72

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.28

Alignment Approved

Sanction on : 20 years 10 months ago

12 Feb 2004

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 2 months 2 weeks from now

15 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

इस कार्यालय के पत्रांक- 3402/3सी0 व0भू0 दि0 05-11-2024 द्वारा क्षतिपूरक वृक्षारोपण भूमि आवंटित करने हेतु जिलाधिकरी महोदय को अनुरोध किया गया है। -- as on 06-Dec-2024

Rating : 0

Forest Case Pending At : 03: DM

Hindrance / Bottleneck : CA Land

Assets :

Work not linked with IM

Bridges on The Basis of AI: