Work Profile Report [2W508]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 5977/।।।(2)/21-52(एम.एल.ए.)/2017 दि0 09.12.2021
TS Amount (lakhs) : 375.36 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
187.68
Resanction Cost :
187.68
Tentative Cost :
167.00
Saving
20.68
Exp. Upto Last Fy :
157.35
For CFY 2024-2025
Remaining :
30.33
Demand :
0.82
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
157.35
In Maintenance After Completion
Sanction on : 2 years 8 months ago
09 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 4 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। प्रथम वर्ष का अनुरक्षण का कार्य किया जा रहा है । -- as on 03-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: