Work Profile Report [2W51]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6419/।।।(2)/10-008(मु.मं.घो.)/10 दि0 9.11.2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
63.00
Resanction Cost :
63.00
Tentative Cost :
63.00
Exp. Upto Last Fy :
0.13
For CFY 2025-2026
Remaining :
62.87
Demand :
0.90
Allotment :
0.83
Exp in CFY :
0.83
Total Up to Date Exp :
0.96
Alignment Approved
Sanction on : 15 years 1 month ago
09 Nov 2010
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समरेखण स्वीकृत। -- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: