Work Profile Report [2W578]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : e file no. 38879 dated 15/03/2023
TS Amount (lakhs) : 179.78 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
179.78
Resanction Cost :
179.78
Tentative Cost :
179.78
Exp. Upto Last Fy :
170.44
For CFY 2025-2026
Remaining :
9.34
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
170.44
Construction Started
Sanction on : 2 years 4 months ago
15 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 2 weeks ago
21 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: