Work Profile Report [2W648]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E file No 48456
TS Amount (lakhs) : 107.91 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
107.91
Resanction Cost :
107.91
Tentative Cost :
107.91
Exp. Upto Last Fy :
29.25
For CFY 2024-2025
Remaining :
78.66
Demand :
78.00
Allotment :
70.00
Exp in CFY :
61.07
Total Up to Date Exp :
90.32
Work completed
Sanction on : 1 year 3 months ago
21 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
100 %
Tentative Completion date on : 4 months 4 weeks ago
28 Jun 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण । -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand