Work Profile Report [2W653]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-File No.56806
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
280.91
Resanction Cost :
280.91
Tentative Cost :
280.91
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
280.81
Demand :
140.00
Allotment :
0.00
Exp in CFY :
109.16
Total Up to Date Exp :
109.26
Construction Started
Sanction on : 1 year 1 month ago
12 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
55 %
Tentative Completion date on : 6 months 1 week from now
11 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
स्कपर व दीवारों का कार्य प्रगति पर। -- as on 02-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand