Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
2W654 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File No.56806
TS Amount (lakhs) : 283.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
283.07
Resanction Cost :
283.07
Tentative Cost :
283.07
Exp. Upto Last Fy : 11.59
For CFY 2024-2025
Remaining : 271.48
Demand : 91.00
Allotment : 0.00
Exp in CFY : 18.10
Total Up to Date Exp : 29.69
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 10 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
9 months 4 weeks from now
16 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 15-Mar-2024
Physical Peramenters