Work Profile Report [2W665]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : 5135(A)/III(2)/2023-01/2023 date 14.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
158.89
Resanction Cost :
158.89
Tentative Cost :
158.89
Exp. Upto Last Fy :
130.59
For CFY 2024-2025
Remaining :
28.30
Demand :
28.00
Allotment :
28.00
Exp in CFY :
27.65
Total Up to Date Exp :
158.23
Work completed
Sanction on : 1 year 1 week ago
14 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on : 2 months 1 week ago
12 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रैश बैरियर व डैलिनेटर लगाने का कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 21-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: