Work Profile Report [2W667]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : 5347/III(2)/2023-01/2023 date 05.12.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
255.59
Resanction Cost :
255.59
Tentative Cost :
255.59
Exp. Upto Last Fy :
141.42
For CFY 2025-2026
Remaining :
114.17
Demand :
0.00
Allotment :
97.55
Exp in CFY :
97.55
Total Up to Date Exp :
238.96
Construction Started
Sanction on : 1 year 7 months ago
05 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
20 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष -- as on 03-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: