Work Profile Report [2W671]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : E file No. 48456 date 30.01.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
67.33
Resanction Cost :
67.33
Tentative Cost :
67.33
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
67.33
Demand :
50.00
Allotment :
20.00
Exp in CFY :
13.13
Total Up to Date Exp :
13.13
Construction Started
Sanction on : 6 months 2 weeks ago
30 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
12 %
Tentative Completion date on : 3 months 3 weeks from now
13 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार व काजवे का कार्य प्रगति पर। -- as on 06-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: