Work Profile Report [2W674]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Efile No. 56806/53 Dt. 23/02/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
310.33
Resanction Cost :
310.33
Tentative Cost :
310.33
Exp. Upto Last Fy :
148.18
For CFY 2025-2026
Remaining :
162.15
Demand :
150.00
Allotment :
109.06
Exp in CFY :
109.06
Total Up to Date Exp :
257.25
Construction Started
Sanction on : 1 year 8 months ago
23 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
55 %
Up to Date :
75 %
Tentative Completion date on : 1 week 1 day ago
26 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.00 कि मी मे पी सी का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 10-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: