Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
2W676 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file no.55597/51 date 07.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
365.54
Resanction Cost :
365.54
Tentative Cost :
365.54
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 365.54
Demand : 37.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 1 week ago
07 Mar 2024
Tentative Completion date:
1 year 1 month from now
01 Sep 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा दि0 12.06.2024 को आमंत्रित की गयी। निविदा प्राप्त। टैक्निकल बिड दिनांक-15.07.2024 को खोली जाएगी। -- as on 01-Jul-2024
Physical Peramenters