Work Profile Report [2W757]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E file 75269/2024 Dt-25-03-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
372.92
Resanction Cost :
372.92
Tentative Cost :
372.92
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
372.82
Demand :
317.00
Allotment :
151.12
Exp in CFY :
151.12
Total Up to Date Exp :
151.22
Construction Started
Sanction on : 9 months 4 weeks ago
25 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
25 %
Tentative Completion date on : 1 month 2 days from now
26 Feb 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कल्वर्ट/दिवार एवं जी3 का कार्य प्रगति पर। -- as on 10-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand