Work Profile Report [30W1111]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1640(ए)/।।।(2)/18-02 (एम0एल0ए0)/2017 दि0 24-04-18
TS Amount (lakhs) : 54.57 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
54.57
Resanction Cost :
54.57
Tentative Cost :
54.57
Exp. Upto Last Fy :
20.82
For CFY 2024-2025
Remaining :
33.75
Demand :
15.00
Allotment :
14.50
Exp in CFY :
14.31
Total Up to Date Exp :
35.13
Alignment Approved
Sanction on : 6 years 6 months ago
24 Apr 2018
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on : 1 year 3 weeks ago
31 Oct 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समरेखण स्वीकृत।द्वितीय चरण (स्टेज-।) लागत रू0 62.70 लाख की स्वीकृति प्राप्त। मुआवजा वितरण किया जा रहा है। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: