Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.100 | 0.4 | 0.400 | 0.000 |
30W1151 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 1234/।।।(2)/19-03 (एम0एल0ए0)/17 टी0सी0 दि0 06-03-19
TS Amount (lakhs) : 254.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
254.03
Resanction Cost :
254.03
Tentative Cost :
254.03
Exp. Upto Last Fy : 225.67
For CFY 2024-2025
Remaining : 28.36
Demand : 5.00
Allotment : 5.00
Exp in CFY : 1.98
Total Up to Date Exp : 227.65
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
5 years 4 months ago
06 Mar 2019
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.10 किमी0 लम्बाई मे पहाड़ कटान का कार्य पूर्ण। शेष भाग मे विवाद है। दायित्वों का भुगतान शेष। -- as on 07-May-2024
Physical Peramenters