Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
30W1225 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 658/।।।(2)/19-03(एम0एल0ए0)/17 टी0सी0 दि0 13-02-2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
32.48
Resanction Cost :
32.48
Tentative Cost :
32.48
Exp. Upto Last Fy : 1.30
For CFY 2024-2025
Remaining : 31.18
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.30
Survey work done
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
4 years 5 months ago
13 Feb 2020
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0पी0आर0 मुख्य अभियन्ता लो0नि0वि0, देहरादून के पत्रसं0- 119/6(12)याता0-स्तर-। (क्षे0का0)/23 दिनांक 06-01-24 द्वारा रू0 50.81 लाख की गठित कर शासन को पे्रषित। -- as on 01-Mar-2024
Physical Peramenters