Work Profile Report [30W1249]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 104/रा0यो0आ0/जि0यो0/2020-21 दि0 05-11-20
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
336.67
Resanction Cost :
336.67
Tentative Cost :
336.67
Exp. Upto Last Fy :
0.51
For CFY 2024-2025
Remaining :
336.16
Demand :
3.00
Allotment :
1.49
Exp in CFY :
0.00
Total Up to Date Exp :
0.51
Survey work done
Sanction on : 4 years 2 weeks ago
05 Nov 2020
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
10 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि प्रस्ताव गठन की कार्यवाही की जा रही है। -- as on 03-Mar-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: