Work Profile Report [30W1428]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 136/रा0यो0आ0/जि0यो0/2022-23
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.00
Resanction Cost :
8.00
Tentative Cost :
8.00
Exp. Upto Last Fy :
2.52
For CFY 2024-2025
Remaining :
5.48
Demand :
5.47
Allotment :
5.47
Exp in CFY :
5.48
Total Up to Date Exp :
8.00
Construction Started
Sanction on : 1 year 9 months ago
24 Jan 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 10 months 3 weeks ago
31 Dec 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 25-Jan-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: