Work Profile Report [30W1461]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ENC Letter No. 895/07Yata-PMGSY-Ni. III
TS Amount (lakhs) : 66.03 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.03
Resanction Cost :
66.03
Tentative Cost :
66.03
Exp. Upto Last Fy :
24.61
For CFY 2024-2025
Remaining :
41.42
Demand :
41.42
Allotment :
35.00
Exp in CFY :
20.00
Total Up to Date Exp :
44.61
Work completed
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वो का भुगतान शेष। -- as on 21-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: