Work Profile Report [30W1524]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : DM Letter No. 1417/13-Aa.Pra.Praa/NON SDRF-23-24
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
9.26
Resanction Cost :
9.26
Tentative Cost :
9.26
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
9.26
Demand :
9.26
Allotment :
4.63
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 1 year 1 week ago
08 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 4 months 2 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 16-Feb-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: