Work Profile Report [30W1533]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No. 124590
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
350.00
Resanction Cost :
350.00
Tentative Cost :
350.00
Exp. Upto Last Fy :
115.39
For CFY 2025-2026
Remaining :
234.61
Demand :
0.00
Allotment :
20.94
Exp in CFY :
20.94
Total Up to Date Exp :
136.34
Construction Started
Sanction on : 2 years 1 month ago
25 May 2023
Physical Progress:
At start of FY 2025-2026 :
55 %
Up to Date :
55 %
Tentative Completion date on : 3 months 3 weeks from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 08-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand