Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11 | 11 | 0.000 | 11 | 11.000 | 0.000 |
30W1534 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No. 56385
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
212.43
Resanction Cost :
212.43
Tentative Cost :
212.43
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 212.43
Demand : 212.43
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
4 months 2 days ago
15 Mar 2024
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दिनांक 05.06.2024 को निविदायें आमन्त्रित कर ली गई है। दिनांक 11.07.2024 को निविदायें प्राप्त की जायेगी। -- as on 03-Jul-2024
Physical Peramenters