Work Profile Report [30W1543]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 388/14याता0(क)-उ0/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
48.15
Resanction Cost :
48.15
Tentative Cost :
48.15
Exp. Upto Last Fy :
44.74
For CFY 2025-2026
Remaining :
3.41
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
44.74
Work completed
Sanction on : 1 year 3 months ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 months 1 week ago
31 Mar 2025
Actual Completion Date : 3 months 3 weeks ago
15 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand