Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.49 | 7.49 | 7.49 | 0 |
30W1544 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 388/14याता0(क)-उ0/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
112.35
Resanction Cost :
112.35
Tentative Cost :
112.35
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 112.35
Demand : 112.35
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 2 days ago
15 Mar 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदाऐं प्राप्त। निविदाओं का निस्तारण किया जा रहा है। -- as on 29-Jun-2024
Physical Peramenters