Work Profile Report [30W1547]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 388/14याता0(क)-उ0/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
32.10
Resanction Cost :
32.10
Tentative Cost :
32.10
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
32.10
Demand :
32.10
Allotment :
10.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Work completed
Sanction on : 8 months 1 week ago
15 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व अवशेष। -- as on 08-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand