Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.25 | 6.25 | 0.000 | 6.25 | 6.250 | 0.000 |
31W242 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शासनादेश सं0 5377(1)/।।।(2)/ 12-13 (मु0मं0घो0)/2012 दिनांक 14.01.2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
78.75
Resanction Cost :
78.75
Tentative Cost :
78.75
Exp. Upto Last Fy : 6.27
For CFY 2024-2025
Remaining : 72.48
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 6.27
Survey work done
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
11 years 6 months ago
14 Jan 2013
Tentative Completion date:
5 years 3 months ago
31 Mar 2019
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: Long Term Forest Approval
भारत सरकार पर्यावरण एवं जलवायु मंत्रालय के पत्रांक 8वी0/यू0सी0पी0/06/157/2016/एम0सी0/2321 दिनांक 17.01.2020 एवं पत्रांक 8वी0/यू0सी0पी0 /06 /157/2016/777/2321 दिनांक 29.7.2020 द्वारा प्रस्ताव को 02 बार निरस्त किया गया है जिसमें उल्लेख किया गया है कि प्रस्तावित ग्राम पूर्व से ही मुख्य मार्ग पर स्थित है। प्रस्तावित मार्ग आलवेदर एन0एच0 -34 के समान्तर प्रस्तावित किया गया है तथा एन0एच0 के अतिरिक्त भी ग्राम को जोड़ने हेतु एक पक्का मार्ग पूर्व से उपलब्ध है। अतः प्रस्तावित मार्ग का कोई औचित्य प्रतीत नहीं होता है। गंगोत्री धाम के पुरोहितो की निरन्तर माॅग पर वन विभाग से वार्ता कर पुनःरीक्षित प्रस्ताव 9 मी0 के स्थान पर 07 मी0 चैडाई में गठित कर पुनः दिनांक 26/07/2023 को आनलाईन प्रेषित किया गया था, जिस पर प्रभागीय वनाधिकारी उत्तरकाशी द्वारा प्रस्ताव में कमिया इगिंत कर प्रस्ताव खण्ड को वापस कर दिया गया है। इंगित कमियों इंगित कमियों का निराकरण कर प्रस्ताव पुनः दिनांक 28.06.2024 को आॅनलाइन कर लिया गया है। -- as on 14-Jul-2024
Physical Peramenters