Work Profile Report [31W30]

भटवाडी में झाला व हर्षिल के मध्य सियागाड पर पैदल पुल।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : -शा0सं0-121/लो0नि0/04-07(प्रा0आ0)/04 दि0 12.02.2004

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Bridges State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

165.75

Resanction Cost :

165.75

Tentative Cost :

165.75

Exp. Upto Last Fy :

18.55

For CFY 2025-2026

Remaining :

147.20

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

18.55

Work deferred

Sanction on : 21 years 1 month ago

02 Dec 2004

Physical Progress:

At start of FY 2025-2026 :

95 %

Up to Date :

95 %

Tentative Completion date on : 1 year 10 months from now

30 Nov 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (105m)
1 (105m)
1 (105m)
-

Remark

view all

ई-डी.पी.आर. आपत्तियों में प्राप्त, आपत्तियों का निराकरण किया जा रहा है। -- as on 31-Dec-2025

Rating : 95

No Forest Case in The Work

Hindrance / Bottleneck : Sanction Required form Govt

Assets :

Work not linked with IM

Bridges on The Basis of AI: