Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 3.6 | 0.000 | 3.6 | 3.600 | 0.000 |
31W423 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शा0 सं0- 2308/।।। 2/16-03 एम0एल0ए0 /2015 दि0 11 अगस्त 2016
TS Amount (lakhs) : 5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy : 1.57
For CFY 2024-2025
Remaining : 3.43
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.57
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 11 months ago
11 Aug 2016
Tentative Completion date:
5 years 3 months ago
31 Mar 2019
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
उक्त कार्य का वनभूमि प्रस्ताव आपत्तयों में खण्ड को लौटाया गया था। आपत्तियों का निराकरण कर वनभूमि प्रस्ताव दिनांक 08/05/2023 को डी0एफ0ओ0 उत्तरकाशी को प्रेषिण के उपरान्त प्रस्ताव भारत सरकास स्तर पर है। -- as on 14-Jul-2024
Physical Peramenters