Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.7 | 0.7 | 0.700 | 0 | 0.000 | 0.000 |
31W569 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शासनादेश सं0 2682/।।। 2/19-03 एम0एल0ए0/2017 टी0सी0।।। दि0 22 जुलाई 2019
TS Amount (lakhs) : 47.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
47.19
Resanction Cost :
47.19
Tentative Cost :
47.19
Exp. Upto Last Fy : 45.04
For CFY 2024-2025
Remaining : 2.15
Demand : 2.15
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 45.04
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 11 months ago
22 Jul 2019
Tentative Completion date:
2 years 6 months ago
31 Dec 2021
Actual Completion Date:
2 years 8 months ago
16 Nov 2021
Remark
Bottelneck: no issue
कार्य पूर्ण। अवशेष धनराशि का उपयोग मार्ग के 03 वर्षों के अनुरक्षण हेतु किया जाना है। -- as on 02-Mar-2024
Physical Peramenters