Work Profile Report [31W774]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश सं0 ई0 फाईल सं0 45771 लो0नि0वि0 अनुभाग 2 दि0 28 फरवरी 2023
TS Amount (lakhs) : 128 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
128.00
Resanction Cost :
128.00
Tentative Cost :
128.00
Exp. Upto Last Fy :
33.84
For CFY 2024-2025
Remaining :
94.16
Demand :
50.00
Allotment :
50.00
Exp in CFY :
0.00
Total Up to Date Exp :
33.84
Construction Started
Sanction on : 1 year 5 months ago
28 Feb 2023
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
50 %
Tentative Completion date on : 1 week 6 days from now
30 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण पार्ट-1 का कार्य 50 प्रतिशत पूर्ण। शेष कार्य प्रगति पर है। -- as on 14-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: