Work Profile Report [31W774]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 ई0 फाईल सं0 45771 लो0नि0वि0 अनुभाग 2 दि0 28 फरवरी 2023
TS Amount (lakhs) : 128 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
128.00
Resanction Cost :
128.00
Tentative Cost :
114.03
Saving
13.97
Exp. Upto Last Fy :
33.84
For CFY 2024-2025
Remaining :
94.16
Demand :
15.00
Allotment :
50.00
Exp in CFY :
4.07
Total Up to Date Exp :
37.91
Construction Started
Sanction on : 1 year 9 months ago
28 Feb 2023
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
60 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 13.97 has been recorded as expected cost of work reduced from 128 to 114.03 . -- as on 30-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand