Work Profile Report [31W781]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0- ई फाईल सं0 49297 दि0 20 मार्च 2023।
TS Amount (lakhs) : 14.39 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
14.39
Resanction Cost :
14.39
Tentative Cost :
11.72
Saving
2.67
Exp. Upto Last Fy :
11.72
For CFY 2025-2026
Remaining :
2.67
Demand :
2.67
Allotment :
2.58
Exp in CFY :
0.00
Total Up to Date Exp :
11.72
Phase1 DPR Submitted
Sanction on : 2 years 9 months ago
20 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
98 %
Tentative Completion date on : 6 months 6 days ago
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 2.67 has been recorded as expected cost of work reduced from 14.39 to 11.72 . -- as on 31-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: