Administrative Approval Detail : शासनादेश सं0- ई फाईल सं0 37632 दि0 24 मार्च 2023।
TS Amount (lakhs) : 20.44 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
20.44
Resanction Cost :
20.44
Tentative Cost :
20.44
Exp. Upto Last Fy :
18.21
For CFY 2024-2025
Remaining :
2.23
Demand :
2.23
Allotment :
2.00
Exp in CFY :
2.00
Total Up to Date Exp :
20.21
Work completed
Sanction on : 1 year 9 months ago
24 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 02-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: