Work Profile Report [31W795]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासन की ई-फाईल संख्या 37632 दि0 28/08/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
123.53
Resanction Cost :
123.53
Tentative Cost :
123.53
Exp. Upto Last Fy :
20.86
For CFY 2024-2025
Remaining :
102.67
Demand :
102.67
Allotment :
50.00
Exp in CFY :
48.18
Total Up to Date Exp :
69.03
Construction Started
Sanction on : 11 months 2 weeks ago
28 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
70 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य 70 प्रतिशत पूर्ण शेष कार्य प्रगति पर है। -- as on 14-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand