Work Profile Report [31W854]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 5082/।।।(2)/2023-01 (प्रा0आ0)/2023 दि0 09 नवम्बर 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
233.90
Resanction Cost :
233.90
Tentative Cost :
233.90
Exp. Upto Last Fy :
153.41
For CFY 2024-2025
Remaining :
80.49
Demand :
80.48
Allotment :
80.48
Exp in CFY :
70.00
Total Up to Date Exp :
223.42
Construction Started
Sanction on : 10 months 1 week ago
09 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on : 3 months 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 02-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: