Work Profile Report [31W862]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासन की ई0 फाईल संख्या 56385 दिनांक 15 मार्च 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
360.99
Resanction Cost :
360.99
Tentative Cost :
360.99
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
360.99
Demand :
360.99
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
none
Sanction on : 5 months 1 day ago
15 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 week 6 days from now
30 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुगन्ध गठन की कार्यवाही प्रगति पर है। -- as on 05-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: