Work Profile Report [32W1204]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्र सं. 541/जि.यो. दिनांक 10.12.2012
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.00
Resanction Cost :
4.00
Tentative Cost :
4.00
Exp. Upto Last Fy :
2.34
For CFY 2024-2025
Remaining :
1.66
Demand :
1.66
Allotment :
1.61
Exp in CFY :
1.61
Total Up to Date Exp :
3.95
Work completed
Sanction on : 12 years 2 weeks ago
10 Dec 2012
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 24-Apr-2024
Assets :
Work not linked with IM