Work Profile Report [32W1212]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO E-file no. 31503, dt. 15-03-2022
TS Amount (lakhs) : 47.52 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.52
Resanction Cost :
47.52
Tentative Cost :
47.52
Exp. Upto Last Fy :
47.33
For CFY 2025-2026
Remaining :
0.19
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
47.33
Work completed
Sanction on : 2 years 6 months ago
15 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 months ago
25 Jun 2024
Actual Completion Date : 1 year 3 months ago
25 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 08-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand