Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.35 | 2.35 | 2.000 | 0.35 | 0.000 | 0.000 |
32W1212 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : GO E-file no. 31503, dt. 15-03-2022
TS Amount (lakhs) : 47.52 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
47.52
Resanction Cost :
47.52
Tentative Cost :
47.52
Exp. Upto Last Fy : 35.65
For CFY 2024-2025
Remaining : 11.87
Demand : 11.87
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 35.65
Work completed
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
1 year 4 months ago
15 Mar 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 24-Apr-2024