Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.05 | 2.05 | 2.050 | 0 | 0.000 | 0.000 |
32W1232 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2319/(।)/।।। (2)/21-62 (प्रा.आ.)/2005 टी.सी. ।।, दिनांक 23.07.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
46.12
Resanction Cost :
61.68
Tentative Cost :
46.12
Saving
15.56
Exp. Upto Last Fy : 55.70
For CFY 2024-2025
Remaining : 5.98
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 55.70
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
23 Jul 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 21-Oct-2023
Physical Peramenters