Work Profile Report [32W1321]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता एवं विभागाध्यक्ष, उत्तराखण्ड लोक निर्माण विभाग, देहरादून का पत्रांक 315/14 याता. (क)-उ./2024-25, दिनांक 03.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
86.37
Resanction Cost :
86.37
Tentative Cost :
86.37
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
86.37
Demand :
86.37
Allotment :
86.37
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Work completed
Sanction on : 4 months 2 weeks ago
03 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
95 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 02-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: