Work Profile Report [32W275]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य अभियन्ता, स्तर-। का पत्र सं. 6064(1)/।। (2)/11-37 (प्रा.आ.)/2011, दिनांक 15.11.2011
TS Amount (lakhs) : 50.4 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
50.40
Exp. Upto Last Fy :
16.00
For CFY 2024-2025
Remaining :
34.40
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
16.00
Work completed
Sanction on : 13 years 1 week ago
15 Nov 2011
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
95 %
Tentative Completion date on : 1 year 4 months from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रतिकर बांटा जाना है। द्वितीय चरण का कार्य पूर्ण। -- as on 23-May-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand