Work Profile Report [32W307]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 2195/(1)/।।। (2)/13-47 (प्रा.आ.)/2012, दिनांक 22.03.2013
TS Amount (lakhs) : 63 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
63.00
Resanction Cost :
63.00
Tentative Cost :
63.00
Exp. Upto Last Fy :
49.61
For CFY 2024-2025
Remaining :
13.39
Demand :
13.39
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
49.61
Work completed
Sanction on : 11 years 9 months ago
22 Mar 2013
Physical Progress:
At start of FY 2024-2025 :
85 %
Up to Date :
85 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वन भूमि की स्वीकृति प्राप्त। प्रतिकर वितरण गतिमान है। fद्वतीय चरण का कार्य पूर्ण। -- as on 06-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: