Work Profile Report [33W1219]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 5727/III(2)/21-16(प्रा0आ0)
TS Amount (lakhs) : 76.68 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.68
Resanction Cost :
76.68
Tentative Cost :
76.68
Exp. Upto Last Fy :
84.62
For CFY 2025-2026
Remaining :
-7.94
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
84.62
Work completed
Sanction on : 3 years 7 months ago
30 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 10 months ago
31 Aug 2022
Actual Completion Date : 2 years 9 months ago
13 Sep 2022
Physical Linear Components
Remark
कार्य पूर्ण. -- as on 31-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand