Work Profile Report [33W1363]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E fil e no. 48419
TS Amount (lakhs) : 187.68 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
187.68
Resanction Cost :
187.68
Tentative Cost :
187.68
Exp. Upto Last Fy :
74.70
For CFY 2024-2025
Remaining :
112.98
Demand :
112.98
Allotment :
52.00
Exp in CFY :
53.02
Total Up to Date Exp :
127.71
Work completed
Sanction on : 1 year 1 week ago
08 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
100 %
Tentative Completion date on : 1 month 4 weeks ago
20 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पुर्ण। -- as on 27-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: